Every manager asks the same thing before a repaint: how long does commercial painting take, and how long will we be disrupted? There is no single answer, because a small shop front and a multi-storey building are different projects. What you can do is understand what sets the timeline, so you can plan around it and ask sensible questions when you get a quote. This guide covers the stages of a commercial job, the factors that stretch or shrink the schedule, and how to avoid delays.
Quick answer: The time a commercial paint job takes depends on the area, the amount of preparation, the number of coats, access, curing time and how the work is staged around your business.
- Preparation often takes longer than painting
- Each coat needs to dry before the next
- Water-based paint takes around a week to cure fully
- Staging around trading hours adds days but protects your business
The stages of a commercial painting job
Most commercial jobs follow the same sequence, and each stage has its own timing. First comes the site visit and written scope. Then there is approval time on your side, which can include a landlord, a centre manager, an owners corporation or a head contractor. Next come ordering products, booking access equipment and agreeing start dates. Only then does the on-site work begin: preparation, priming, coating, inspection and handover.
Most delays happen before anyone lifts a roller. Colour decisions are a common holdup, especially when several people have to agree, so book a colour consultation early if the palette is not settled. Product ordering can also take a few days when a custom tint is needed, and access equipment has its own booking lead time. A scope that has been agreed early, with clear colours and access arrangements, can start sooner than one still waiting on approvals. If your building is part of a strata scheme, see our strata painting page for how approvals fit in.
What makes a repaint faster or slower
- Size: more surface area means more hours and often more people on site
- Condition: flaking paint, cracks, rust and mould add preparation
- Height: scaffold or platform set-up and the safety planning that goes with it
- Coating system: primers, number of coats and specialist products
- Weather: exterior work waits for dry, mild days
- Working hours: after-hours or staged work spreads the job over more days
- Approvals: landlord, centre or committee sign-off before start
Weather is a good example. Exterior coatings are applied in suitable conditions, and rain, strong wind or very hot surfaces can pause work. Coastal sites, such as those along the Illawarra, can add salt washing to the preparation stage.
Drying and curing take time
Paint feels dry long before it is fully cured. The Dulux maintenance guide on DuSpec+ says water-based paints appear to dry quickly but take around a full week under normal climatic conditions to cure and develop full washability, and suggests waiting before washing marks. For busy spaces, that is a reason to schedule heavy cleaning or furniture moves after the first few days.
Multiple coats are separated by recoat times set by the product’s data sheet. We follow those times, because rushing coats can cause poor adhesion and an uneven finish.
Access and safety planning take time too
Work above two metres needs planning. SafeWork NSW’s working at heights guidance says a site-specific safe work method statement is required for construction work where a person could fall more than two metres, and that working from the ground or solid construction is always the safest option. Booking scaffold or an elevating work platform and preparing the paperwork is part of the lead time on taller buildings.
Older buildings can add another step. SafeWork NSW’s lead notification page says notification for lead risk work is due up to seven days before work starts. If testing finds lead in old paint, the plan changes, and lead paint removal is arranged via a specialist contractor.
Staging around your business
Painting an occupied site rarely happens in one block. Work is staged in zones, with entrances, corridors and key rooms painted in a planned order so the business keeps functioning. That adds days compared with an empty building, but it protects trade. Our Ampol Barrack Heights store interior page shows how shelving and fixtures can be covered while a ceiling is painted, which is a good picture of the protection work that goes into retail jobs.
For shops, offices and industrial sites, the shape of the stages is different. Our pages for shopfront and retail painting, office painting and industrial painting explain how the staging changes by building type.
How to avoid delays
- Confirm who must approve colours and scope before you book
- Provide access details, parking and site rules early
- Clear furniture, stock and equipment from the work area
- Tell us about trading peaks and events that need a clear site
- Keep variations to one decision-maker, not many
Ask your painter for a written program with dates, zones and handover steps, and check how weather delays are handled. For a scope and timeline on your site, see our commercial painting page, the page for commercial painters in Wollongong, or contact us. WM Painting & Decorating is licensed and insured, with 10+ years in the trade.
FAQs
Is there a standard duration for commercial painting?
No. The time depends on the building, the preparation and how the work is staged. A written scope after a site visit is the only reliable way to get a realistic program.
Why does preparation take so long?
Washing, repairing and priming decide how well the paint lasts. Skipping them saves time on the day but shortens the life of the finish.
Can painting be done after hours to save time?
It can reduce disruption, though it does not always shorten the job. Work in quiet hours can progress faster because there is nobody in the way, but it may be spread over more evenings.
How long before the paint is fully cured?
Water-based paint takes around a week under normal conditions to cure fully, according to the Dulux maintenance guide. Light use is usually possible sooner, but wait before scrubbing walls.
What causes the most delays on commercial jobs?
Late approvals, access problems and weather. Agreeing the scope, colours and site access early prevents most of them.